We are so excited to share some of what God has done on this journey from purchasing a permanent building in White Post, VA through its many phases of use and repairs, to its renovation. On November 13th, 2022 we held a Dedication Ceremony after the sanctuary renovation was finally finished. We hope you enjoy our journey in pictures through the many changes!
Our Renovation Story in Pictures
- 
    2/28/22 - Pews removed and we are ready for demolition! 
- 
    3/1/22 - Demolition began! 
- 
    3/8/22 - Dumpster arrived and new windows being cut out and framed! 
- 
    3/8/22 - View of window from the inside 
- 
    3/9/22 - Stage is framed 
- 
    3/10/22 - Windows cut out, framed, and boarded up until glass arrives in a few months 
- 
    3/15/22 - More progress on the stage and all seven windows framed and boarded up! Stain glass removed and ready for re-sale. 
- 
    3/21/22 - Outside of the building going North bound on Lord Fairfax Hwy. 
- 
    3/21/22 - Narthex was framed and partition wall framed. 
- 
    3/21/22 - Sacristy floors removed and cinder block foundation walls found. 
- 
    3/21/22 - A look at the sanctuary this week. 
- 
    3/28/22 - Privacy Wall in the Narthex 
- 
    4/4/22 - Ceiling arches are coming soon! 
- 
    4/11/22 - Initial work for exterior siding begins 
- 
    4/11/22 - Exterior of north side of church 
- 
    4/11/22 - Ceiling prep for beams continues 
- 
    4/25/22 - Exterior Siding nearly complete 
- 
    4/25/22 - Narthex window reframed 
- 
    4/25/22 - Meeting with architect, general contractor, electrical contractor, AV provider, and project managers. Looking at the space together. 
- 
    4/25/22 - God has brought together an amazing team of people to build this space for God's glory! 
- 
    5/27/22 - Stonework has begun in the Narthex 
- 
    5/27/22 - Stonework has begun in the Sanctuary 
- 
    6/6/22 - The stone work in the sanctuary and Narthex are finished! This picture is from the sanctuary. 
- 
    6/6/22 - A wider picture of the sanctuary with the finished stone work! 
- 
    8/15/22 - Drywalling has begun! 
- 
    8/15/22 - Picture of the drywalling from further back 
- 
    8/29/22- More drywalling completed and painting has started! 
- 
    8/29/22 - Look at all that light! Thank you, Lord, for progress on this beautiful space! 
- 
    9/5/22 - Board, batten, and drywall going in! 
- 
    
- 
    10/9/22 - Red Zone Planning Meeting 
- 
    10/9/22 - Sanctuary and Narthex Crosses have arrived! 
- 
    10/13 - Jerusalem Cross is being installed in the Narthex 
- 
    10/21/22 - The windows have finally arrived and been installed! Pictured: one excited senior warden, worship director, and rector! 
- 
    10/21/22- View from back of sanctuary 
- 
    10/21/22- View from pulpit 
- 
    10/21/22- Narthex window and Jerusalem cross 
- 
    10/28/22 - Cross was hung in the sanctuary this week! 
- 
    10/28/22 - Another picture of the cross at the front of the sanctuary 
- 
    10/28/22 - Evening light coming through the new windows 
- 
    10/28/22 - New tile in the Narthex bathrooms 
- 
    11/7/22 - Exterior painting and trim 
- 
    11/7/22 - Exterior picture #2 
- 
    11/7/22 - Interior Painting in the hallway 
- 
    11/7/22 - New sconces in the hallways 
- 
    11/11/22 - Floors are finished in the sanctuary! 
- 
    11/11/22 - Floors are finished in the sanctuary! 
- 
    11/17/22 - Doors in the sanctuary are hung! 
- 
    11/17/22 - View of the doors from the Narthex 
- 
    11/17/22 - Night views of the church all lit up! 
- 
    11/17/22 - View of the church at night from the front entrance! 
- 
    11/20/22 - Our first Sunday in the building! Dedication Ceremony and Celebration! 
- 
    11/22/22 - Pews are being installed! 
- 
    11/22/22 - Another picture of the pews from further back in the sanctuary.